As we enter into the last month of 2021 it is exciting to see significant works happening at Cabana Palm Beach, with basement one and two now poured.

Heading in to January, 2022, be on the look out for scaffolding and cranes on site as the ground floor is poured and the pre-cast fluted facade begins to arrive.

 

Construction Timeline

  • 9 November 2021 – Basement two poured and reinforced
  • 7 December 2021 – Basement one poured and reinforced
  • 10 January 2022 – Ground floor pour
  • Mid January 2022 – First arrival of pre-cast fluted facade
  • Mid January 2022 – Perimeter scaffold going up

Preparing for Absolute Beachfront Luxury

Situated in Palm Beach, one of the top five most searched suburbs in Queensland, Cabana lies directly opposite the recently completed artificial reef, making it a surfer’s dream.

Cabana Palm Beach is due for completion by the end of 2022.